The 9 p.m. search that starts this

You just finished a whole-house remodel in Lakewood. Contract was $80,000, you wrote two change orders, and the final draw cleared. Then your books say the job made $8,000 instead of the $18,000 you priced — and you're typing "remodeling contractor accountant Dallas" into your phone at 9 p.m. because you can't tell where the other ten grand went.

Here's the honest answer: it didn't go anywhere. It was never recorded. That's a bookkeeping and job-costing problem, and it gets solved with four specific things — not with a vague retainer.

What a remodeling contractor accountant in Dallas actually does — and what's excluded

Stream does four things for remodelers: bookkeeping, job costing, WIP tracking, and tax preparation. That's the whole list, and the list matters more than the label.

Bookkeeping means every transaction lands in the right place — including payroll and vendor bills reconciled into the books. You run payroll and you buy the material; the job is making sure the books tell the truth about both.

Job costing means every dollar carries a cost code — a label that ties a cost to a job and a category, like "Demo – Labor" or "Cabinets – Material." WIP tracking means work-in-progress reporting: a monthly statement showing what each open job has earned versus what you've billed it.

What's excluded, plainly: no tax planning engagements, no payroll processing, no AP/AR run for you, no sales tax filings, no audits, reviews, or compiled financial statements.

Before the job: cost codes and a burdened labor rate

Most remodelers lose margin at the bid, not the build. You price a lead carpenter at the $34 an hour you pay him. That number is wrong before he unlocks the truck.

Your burdened rate is wage plus employer payroll taxes, workers' comp, liability, vehicle, and phone. Say that carpenter's burden adds $10 an hour: you're bidding $34 and spending $44. On a job with 400 crew hours, that gap is $4,000 you never priced.

The fix before the job starts is boring and permanent. Lock a cost code list you'll use on every job — Demo, Framing, Rough Trades, Drywall, Tile, Cabinets, Trim, Punch — and bid in those same buckets so the estimate and the actuals compare line for line.

During the job: change orders and draws are two different numbers

Remodeling is the trade where change orders decide the year. Homeowner picks a different tile, moves a wall, adds a niche. If that work gets built before it gets papered and billed, you financed it.

The rule I'd hold to: no change order gets scheduled until it's signed and added to the contract value in the books. Not "we'll settle up at the end." Signed, priced, recorded.

Overbilling is billing ahead of the work you've actually completed — cash in the bank that isn't profit yet. Most remodelers are overbilled early because the deposit lands before the demo does, and they spend it like it's margin.

A $90,000 kitchen, run through the numbers

Say the contract starts at $80,000. Two change orders: $6,000 for a relocated gas line, $4,000 for upgraded countertops. Revised contract value is $90,000.

You estimated total cost at $72,000, so the job was priced to make $18,000 — a 20% margin on $90,000.

Now assume you're mid-build with $54,000 of coded cost on the books. Percent complete is $54,000 ÷ $72,000 = 0.75, or 75%. Earned revenue is 0.75 × $90,000 = $67,500.

You've billed $75,000 in draws. Overbilling is $75,000 − $67,500 = $7,500. That $7,500 is the homeowner's money sitting in your account — not profit, and not available for the next deposit.

Here's the part that stings. If those two change orders never made it into the contract value and never got billed, you built $10,000 of work for free. Your $18,000 gross profit becomes $8,000. Same crew, same tile, half the margin — decided by paperwork.

After the job: closeout, retainage, and the January 31 deadline

Retainage is the slice a customer or GC holds back until final acceptance — commonly held on the larger builder and commercial work Dallas remodelers pick up between residential jobs. It's revenue you've earned and cash you don't have. It belongs on the balance sheet as a receivable, not forgotten in a folder.

Closeout is also where subcontractor reporting gets decided, and remodelers use more subs than almost anyone — tile, electrical, plumbing, glass, countertop fabrication. For tax year 2026, the Form 1099-NEC reporting threshold for nonemployee compensation is $2,000. Statements go to the payee and to the IRS by January 31.

That deadline is only survivable if sub payments were coded to a vendor all year. Reconstructing them in January from bank memos is how remodelers end up filing wrong or filing late.

Monthly books versus catching up in the spring

Two real options, so weigh them side by side.

Monthly closes give you a WIP report while you can still act on it — you find the underbilled change order in March, not next February. Annual catch-up tells you the truth after it's too late to bill anybody.

My verdict: if you carry more than two open jobs at a time or your customers pay by draw, monthly wins and it isn't close. If you're a one-truck handyman operation with same-day invoices, annual is defensible. Either way, monthly bookkeeping is the version that changes decisions instead of just filing them.

On the tax side, an entity extension runs through Form 7004, and individual returns have their own extended federal due date. An extension moves the filing, not the money.